Contractor Invoice Generator by Veystrum

Schedule of values · retainage · PDF

Progress billing pay application generator

List the lines of your schedule of values, enter what was done this period and what's stored on site, and get the amount due after retainage and earlier requests. Then roll it forward for next month.

1. Project and parties

2. This application

3. Contract and retainage

Filled in for you when you start the next application.

Approved change orders

4. Schedule of values

One row per line of the contract breakdown. "Billed before" is the work on that line in earlier applications; "Stored on site" is material delivered but not yet installed.

Summary

Contract value

Original contract
$0.00
Approved change orders (net)
$0.00
Adjusted contract value
$0.00

Work to date

Completed work
$0.00
Materials stored on site
$0.00
Completed and stored
$0.00
Held on completed work
$0.00
Held on stored materials
$0.00

This application

Earned after retainage
$0.00
Already requested
$0.00
Amount due now
$0.00
Total retainage held
$0.00
Left to bill, incl. retainage
$0.00

5. Schedule of values sheet

LineWork itemValueBilled beforeThis periodStored on siteTo dateLeft to bill% doneRetainage

The arithmetic, line by line

For each line: to date = billed before + this period + stored on site; left to bill = value − to date; % done = to date ÷ value. Retainage on a line is the completed-work rate × (billed before + this period) plus the stored-materials rate × stored on site, each rounded to the cent.

For the application: earned after retainage = completed and stored − total retainage; amount due now = earned after retainage − already requested; left to bill = adjusted contract value − earned after retainage, which includes the retainage still to be released.

Running it month after month

When the application is approved and paid, press Start the next application. Your draft moves forward one period in this browser, ready for next month's figures. Keep a PDF of each application you send; the draft only holds the latest one.

About the AIA forms

Many owners and lenders ask for pay applications on the AIA G702 and G703 forms. This page doesn't reproduce those documents. It produces its own summary and schedule-of-values sheet that show the same kind of figures, which suits contracts that let you choose the format, and checking your numbers before you fill in an official form.

Pay application questions

Is this the same as an AIA G702 and G703?

It does the same kind of arithmetic as an AIA G702/G703 pay application, but it is our own form with our own layout and wording. If your contract requires the official AIA documents, use those; you can still use this tool to check the numbers.

Why are there two retainage rates?

Many contracts hold back a different percentage on materials stored on site than on installed work, and some hold nothing back on stored materials. Enter each rate separately; set either to 0 if it doesn't apply.

What happens when I start the next application?

Everything billed so far moves into 'billed before', 'this period' clears, the application number goes up by one, and the amount earned after retainage becomes 'already requested'. Stored materials stay until you move them into installed work.

Why doesn't my schedule of values match the contract?

The values of all lines should add up to the original contract plus approved change orders. Add each approved change order as a line, or adjust the values, until the check message disappears.

AIA, G702 and G703 are trademarks of The American Institute of Architects. This tool is not affiliated with or endorsed by AIA.